Sewer Repair Activity Log
3/21/2022
Work done today
Work done today
- Identified the manholes in the property.
- Cleaned from manhole 1 to manhole 3.
- Dug the areas with issues.
- Pulled out the ground rod from the pipe.
- Repaired top part of the 6" pipe that has been opened to be able to cut the rod.
- Grounded rod in 6” clay pipe (run from MH-1 to MH-3).
- Continued the inspection and the cleaning process.
3/22/2022
Work done today:
Work done today:
- All runs video inspections.
- None.
- Start cleaning all runs.
3/23/2022
Work done today.
After cleaning notes for Run #6.
After cleaning notes for Run #7.
After cleaning notes for Run #4.
Work done today.
- Run #6 MH12 to MH11 has been cleaned.
- Run #7 MH11 to MH8 has been cleaned.
- Run #11 MH11 to MH15 started to be cleaned.
After cleaning notes for Run #6.
- Pipe size.......................................8" clay.
- Lateral attached..........................0.
- Pipe conditions............................Small crack.
- Extra work before been lined......no.
- Distance.......................................+/-111 ft.
- Ready to be lined.........................yes.
After cleaning notes for Run #7.
- Pipe size.......................................8" clay.
- Lateral attached..........................0.
- Pipe conditions............................Good
- Extra work before been lined......no.
- Distance.......................................+/- 190
- Ready to be lined..........................yes.
After cleaning notes for Run #4.
- Pipe size.......................................6" clay.
- Lateral attached..........................Yes
- Pipe conditions............................Good
- Extra work before been lined......no.
- Distance.......................................+/-380 ft
- Ready to be lined..........................yes.
3/24/2022
Work done today.
After cleaning notes for Run #4.
After cleaning notes for Run #2 ( MH1 to MH3).
After cleaning notes for Run #3 (MH3 to MH4).
Work done today.
- Run #4 MH11 to MH5 ( my mistake for calling it Run 11 yesterday) has been cleaned.
- Run # 2 MH1 to MH3 has been cleaned.
- Run # 3 MH3 to MH4 started to be cleaned.
After cleaning notes for Run #4.
- Pipe size.......................................6" clay.
- Lateral attached..........................14 Units
- Pipe conditions............................ Small cracks, lateral with roots( been cleaned), roots ( been cleaned).
- Extra work before been lined......yes (Unit 26 lateral to main with roots).
- Distance.......................................+/-380 ft
- Ready to be lined..........................yes.
After cleaning notes for Run #2 ( MH1 to MH3).
- Pipe size.......................................6" clay.
- Lateral attached..........................5 Units
- Pipe conditions............................ Good
- Extra work before been lined........no
- Distance.......................................TBD
- Ready to be lined..........................yes.
After cleaning notes for Run #3 (MH3 to MH4).
- Pipe size.......................................6" clay.
- Lateral attached..........................8 Units
- Pipe conditions...........................In the cleaning process.
- Extra work before been lined........TBD
- Distance.......................................TBD
- Ready to be lined..........................TBD
3/28/2022
Work done today, 3/28/2022
Work done today, 3/28/2022
- 80 ft of 8” for the run #6 ( MH11 to MH12) pipe has been lined.
- Built 6” bladders.
- Lining Preparation for tomorrow.
- The CO in the run #4 between MH11 and MH15 has been fixed.
- None.
- Finish line run #6 ( MH11 to MH12).
- Start line run #4 ( MH 11 to MH 15).
- Units from 2 to 12 @ Coves End Drive.
- Unit from 14 to 38 @ Coves End Drive.
- Units from 21 to 39 @ Coves End Drive.
- Units from 14 to 32 @ Garden Drive.
3/29/2022
Work done today.
Work done today.
- 40 ft of 8” for the run #6 ( MH11 to MH12) pipe has been lined.
- 50 ft of 6" for the run #4( MH11 to MH15) pipe has been lined.
- Run #5 MH1 to MH3 has been cleaned.
- None.
- Continue lining run#4 ( MH 11 to MH 15).
- Units from 21 to 39 @ Coves End Drive.
- Units from 14 to 32 @ Garden Drive.
3/30/2022
Work done today.
Issues:
Work for tomorrow:
Water restrictions.
Work done today.
- 57 ft of 6" for the run #4( MH11 to MH15) pipe has been lined.
- 57 ft of 6" for the run #4( MH11 to MH15) pipe has been lined.
- 51 ft of 6" for the run #4( MH11 to MH15) pipe has been lined.
- Run #5 MH4 toMH5 has been cleaned.
Issues:
- None.
Work for tomorrow:
- Continue lining run#4 ( MH 11 to MH 15).
Water restrictions.
- Units from 21 to 39 @ Coves End Drive.
- Units from 14 to 32 @ Garden Drive.
3/31/2022
Sewer Project Work done Thursday - 03/31/22.
Issues:
Work for tomorrow:
Water restrictions.
Sewer Project Work done Thursday - 03/31/22.
- 47 ft of 6" for the run #4( MH11 to MH15) pipe has been lined.
- 60 ft of 6" for the run #4( MH11 to MH15) pipe has been lined.
- 43 ft of 6" for the run #4( MH11 to MH15) pipe has been lined.
- Re-piped CO between MH11 and MH15.
Issues:
- None.
Work for tomorrow:
- Final section line for run#4 ( MH 11 to MH 15).
Water restrictions.
- Units from 21 to 39 @ Coves End Drive.
- Units from 14 to 32 @ Garden Drive.
4/5/2022
Work done 4/4 & 4/5/22.
Work for tomorrow:
Water restrictions.
Work done 4/4 & 4/5/22.
- Run # 1 MH2 to M3 has been re-cleaned.
- 60 ft of 8" for the run #8 ( MH4 to MH5) pipe has been lined.
- 32 ft of 8" for the run #8 ( last section) ( MH4 to MH5) has been lined.
- 60 ft of 6" for the run #1 ( MH2 to MH3) pipe has been lined.
- Run # 5 CO to MH17 has been cleaned.
- None.
Work for tomorrow:
- Finish lining run#1 ( MH2 to MH3).
- Start lining run #5.
Water restrictions.
- Club House.
4/7/2022
Work done on Thursday, 04/07/2022
Work for Monday, 04/11/2022
Homes with Water Restrictions: Monday, 04/11/2022
Red Poinciana Drive
Garden Drive
Work done on Thursday, 04/07/2022
- 17 ft of 6" for the run #5 (CO to MH17) pipe has been lined.
- (4") 2 way CO has been installed.
- None.
Work for Monday, 04/11/2022
- Preparation for shutting run # 2 ( MH1 - MH3).
- Preparation for shutting run# 3( MH3 -MH4).
- Preparation for run# 7 (MH8 - MH11).
Homes with Water Restrictions: Monday, 04/11/2022
Red Poinciana Drive
- Units 39, 36, 35, 34, 33, 32, 31, 30, 29, 28, 27, 25, 23.
- Units 26, 24, 22, 20, 18, 16, 14.
Garden Drive
- Units 31, 29, 27, 25, 23, 21, 19, 17, 15, 13.
4/11/22
Work done today.
Work for Monday.
Water restrictions.
Poinciana Drive
Work done today.
- Run # 2 MH1 to M3 has been re-cleaned.
- 190 ft of 6" for the run # 2 (MH1 to MH3) pipe has been lined.
- One lateral connection with the main has been opened.
- None.
Work for Monday.
- Preparation and shutting run# 3( MH3-MH4).
Water restrictions.
Poinciana Drive
- Units 39, 36, 35, 34, 33, 32, 31, 30, 29, 28, 27, 25, 23.
- Units 26, 24, 22, 20, 18, 16, 14.
- Units 31, 29, 27, 25, 23, 21, 19, 17, 15, 13.
4/12/2022
Work done today.
Work for tomorrow.
Water restrictions.
Coves End Drive
Work done today.
- Run # 3 MH3 to MH4 has been re-cleaned.
- 280 ft of 6" for the run # 3 (MH3 to MH4) pipe has been lined.
- Five ( 5) laterals connection with the main has been opened.
- None.
Work for tomorrow.
- Open last lateral for run #3
- Preparation and shutting run# 7 (MH11 to MH8).
Water restrictions.
Coves End Drive
- Units 38, 37, 24, 22, 20, 18, 16, 14, 12, 10, 8, 6, 4, 2, 39, 37, 35, 33, 31, 29, 27, 25, 23, 21, 19, 17, 15, 13, 11, 9, 7, 5, 3, 1.
- Units 32, 30, 28, 26, 24, 22, 20, 18, 16, 14, 12, 10, 8, 6, 4, 2.
4/14/2022
Work done today.
• Run # 7 MH8 to MH11 has been re-cleaned.
• 190 ft of 8" for the run # 7 (MH8 to MH11) pipe has been lined.
• Cleaned all the working areas.
Issues:
• None.
Note:
• Thanks to all the owners and the association for the support and help they have given us at all times to make the Garden Cove Park lining a successful project.
Regards.
Manny Ruiz
Mechanical Engineer
Blue Works, Inc.
Work done today.
• Run # 7 MH8 to MH11 has been re-cleaned.
• 190 ft of 8" for the run # 7 (MH8 to MH11) pipe has been lined.
• Cleaned all the working areas.
Issues:
• None.
Note:
• Thanks to all the owners and the association for the support and help they have given us at all times to make the Garden Cove Park lining a successful project.
Regards.
Manny Ruiz
Mechanical Engineer
Blue Works, Inc.